Friday, 6 March 2020

Road Work Around Wembley with dates.


As  Brent Council currently have a large amount of works planned in the Wembley Park area I would like to make you aware of the programme.

·        6/3/20 – 8/3/20 – South Way Closed for Crane dismantle

·        9/3/20 – 12/3/20 – Two Way Working – Fulton Road will be closed at the junction of Fifth Way

·        9/3/20 – 12/3/20 – Two Way Working – Carriageway resurfacing on Fourth Way and Fifth Way – this will be undertaken at night keeping one lane open to traffic at all times.

·        10/3/20 – Two Way Working – Fourth Way will be closed at the with South Way / Great Central Way, all traffic will be diverted on to Atlas Road and Hannah Close.

·        13/3/20 – 15/3/20 – Engineers Way will be closed at the junction of First Way to enable a Crane dismantle – all traffic will be diverted via Fulton Road and Rutherford Way.

·        18/3/20 – 20/3/20 – Two Way Working - Engineers Way and First Way will be closed at night for carriageway resurfacing.

·        22/3/20 – Two Way Working – Scheme goes live between 06:30 – 07:30.

·        22/3/20 – 23/3/20 – Two Way Working -  Additional Signage and Marshals will be in place to increase safety as the scheme goes live on all day Sunday and in the morning on Monday.

Better to avoid catching up  in a traffic Jam.