As Brent Council currently have a large amount of works planned in the Wembley Park area I would like to make you aware of the programme.
· 6/3/20 – 8/3/20 – South Way Closed for Crane dismantle
· 9/3/20 – 12/3/20 – Two Way Working – Fulton Road will be closed at the junction of Fifth Way
· 9/3/20 – 12/3/20 – Two Way Working – Carriageway resurfacing on Fourth Way and Fifth Way – this will be undertaken at night keeping one lane open to traffic at all times.
· 10/3/20 – Two Way Working – Fourth Way will be closed at the with South Way / Great Central Way, all traffic will be diverted on to Atlas Road and Hannah Close.
· 13/3/20 – 15/3/20 – Engineers Way will be closed at the junction of First Way to enable a Crane dismantle – all traffic will be diverted via Fulton Road and Rutherford Way.
· 18/3/20 – 20/3/20 – Two Way Working - Engineers Way and First Way will be closed at night for carriageway resurfacing.
· 22/3/20 – Two Way Working – Scheme goes live between 06:30 – 07:30.
· 22/3/20 – 23/3/20 – Two Way Working - Additional Signage and Marshals will be in place to increase safety as the scheme goes live on all day Sunday and in the morning on Monday.